The Omaha Streetcar Authority held a special meeting May 23 to approve a contract to purchase $205,461 in specialty rail to be used for transitions and bridge crossing along the route. The authority became aware that the last domestic mill that produces the rail will shut its doors in 30-45 days. The rail is usually a long-lead-time item, but because the mill is clearing out remaining inventory, the authority can procure the rail earlier and at an advantageous price. The authority also held its regular meeting on May 12, where they heard reports of modest delays in the utility work. The Harney Street replacement bridge is on schedule for completion in 2025. – Isaiah Ang