UNMC Residence Hall Goes Vertical
Construction has gone vertical on the University of Nebraska Medical Center’s first student residence hall near 39th & Dewey Avenue. Crews have framed much of the first three floors. The $66 million, 200,000 sq. ft., 6-story building will accommodate 300 students. Occupancy is scheduled for August 2026.
Bank of America Branch Office in Midtown
A former KFC restaurant site in Midtown will soon be home to a Bank of America branch office. Construction is under way on a 4,275 sq. ft. bank building at 4358 Dodge Street. That’s where a former fast-food restaurant was recently demolished. Located just north of the University of Nebraska Medical Center, this building will be Bank of America’s third location in Omaha. The others are at 13255 West Center Road and 86th & West Dodge Road.
Streetcar Vehicle Maintenance Facility
Site work is well under way on the future 2-story streetcar vehicle maintenance facility on a small portion of the CHI Health Center’s Parking Lot A. The facility is located near to an existing OPPD substation in the shadow of Interstate 480 bridges. The entrance into Lot A had to be reconfigured to accommodate the site. The facility will maintain the six streetcars that will run on the 3.2-mile route connecting The Riverfront, Old Market, downtown, Midtown Crossing, The Blackstone District and the University of Nebraska Medical Center.
Steel Goes Up at OrthoNebraska West Maple
Crews have assembled much of the steel superstructure for a future building northeast of 180th & West Maple Road. That’s where OrthoNebraska’s West Maple Clinic plans to call home. Just to the west of OrthoNebraska, construction is also underway on a retail center. The developer of the project area is White Lotus Group. OrthoNebraska has existing locations near Oakview Mall and in Aksarben Village, Elkhorn and Council Bluffs.
EDGE District Parking Garage at UNMC
Crews are currently working on the fifth and sixth levels of what will be a 7-level parking garage in the University of Nebraska Medical Center’s EDGE District, a multi-use development anchored by the Catalyst Building. The site is situated between 48th Street to the west, Saddle Creed Road to the east, Farnam Street to the north and Leavenworth Street to the south. Located at 4605 Farnam Street, the city-owned garage will provide 753 parking stalls, including four electric vehicle charging stations.
Tenaska Center for Arts Engagement Tour
Grow Omaha recently toured the $108 million Tenaska Center for Arts Engagement under construction at 12th & Douglas Street. The 4-story, 103,000 sq. ft. building is an addition to the east side of the Holland Performing Arts Center. The building will offer additional rehearsal, workshop and classroom spaces to accommodate Omaha Performing Arts’ education and community engagement programs, which already serve more than 100,000 students, teachers and community members each year. A large event venue will also be part of this new center.
Here are a few observations from the tour:
1. The main entrance will be on the north side.
2. The large event hall can be isolated from the education areas. It also has access to the Holland lobby and Douglas Street.
3. Construction will end in December of this year with the opening planned for March 2026.
4. The facility is already booking classes, camps and even weddings.
Photo by Brad Williams
Progress Toward Millwork Commons Parking Garage
The Omaha City Council is reviewing an ordinance to enter into a purchase agreement with Millwork Land Company, LLC, to facilitate development of the Millwork Commons parking garage. Under the agreement, the City will purchase a parcel of land from Millwork Land at the northwest corner of 11th Street and Nicholas Street for $600,000. The City already owns the adjacent parcel. The City is already in the design phase of the parking garage and intends to complete the project by Fall 2026.
Additionally, the City owns four lots on the southwest corner of the same intersection. Millwork Land will have the option to purchase those lots, dependent on when the City builds a connector from 11th Street and Izard to 10th Street and Cuming Street. According to the agreement, if Millwork Land exercises its option, it is committed to build a mixed-use building that will include apartments, artist studios and gallery space, or something similar. That project would largely be bounded by Nicholas, Cuming, 12th and 11th streets. The City would cooperate in the potential vacation of Izard Street as part of the mixed-use building project. – Isaiah Ang
City Council Green Lights Downtown Apartment Building
The Omaha City Council approved the $852,814 Tax Increment Financing application for a multifamily apartment project at 2226 Howard Street. Formerly referred to as Jefferson Place, the project is now being called “The Mueller,” which is the surname of the project’s developers. The $9.58 million project is a four-story building that will fill out the quarter-acre site and house 34 residential units – 27 one-bedroom and 7 two-bedroom. Completion is planned for April 2026. – Isaiah Ang
Sponsored by SEi Security:
Subscribe
To our newsletter
The Catalyst on the EDGE District Campus
The Catalyst, an innovation hub on the University of Nebraska Medical Center’s EDGE District campus, is opening for business. Crews are putting the last, final touches on the 170,000 sq. ft. facility built inside a 119-year-old, former steel-casting factory. UNeMed,...
TreeHouse Mixed-Use Development in Council Bluffs
Crews have made quite a bit of progress on TreeHouse, a mixed-use development in Council Bluffs at First Avenue & 34th Street. That’s just a bit south of West Broadway. When it’s complete, the development will consist of 12 buildings. Two of them will be retail,...
Parking Garage in EDGE District at UNMC
Crews are currently working on the third level of what will be a 7-level parking garage in the new University of Nebraska Medical Center multi-use district anchored by the Catalyst Building. The site is situated between 48th Street to the west, Saddle Creed Road to...
Construction Progress on The Arthur in Midtown
The Arthur, a 329-unit, class-A apartment project is currently under construction at 48th & Dodge Street. The name honors Dr. Arthur Pittman, Omaha’s first African-American veterinarian and a prominent civic leader. His single-story office building is being...
Progress on the CORE Building at UNMC
Construction is coming along quickly on the Center of Research Excellence (CORE) building, located in the University of Nebraska Medical Center’s EDGE District southwest of Farnam Street & Saddle Creek Road. The approximately $105 million, 180,000 sq. ft....
5-Story Apartment Building Downtown
Urban Village is constructing a multi-family project at 1508 Marcy Street. The building is enclosed, and workers are now installing exterior brick. This infill project will be a 5-level building with 82 apartment units and indoor parking on a previously under-utilized...
Former Sinclair on Millard Avenue Demolished
The former Paul’s Sinclair gas station at 13205 Millard Avenue has been demolished. The long-time Millard business included also auto repair and propane services. The new owner plans to redevelop the site with new construction. The actual retail/commercial use has not...
Once a 24-Hour Fitness; Soon to Be Apartments
Construction is wrapping up on a unique multi-family development in northwest Omaha. AVG Partners and Ronco Construction are constructing a 5-story apartment building at 120th & Miami Street in the North Park area. The 160-apartment building is actually being...
Demolition Continues on Old Park Fair Mall
Demolition continued this week at the old Park Fair Mall located on the east side of 16th Street between Douglas and Farnam streets. The mall originally opened in the 1980s but closed many years ago. It most recently served as an indoor parking garage. When it opened...